挪威DeepOcean拿下中国台湾全新海上风电场项目阵列间电缆施工合同
作者: 发布时间:2026年04月23日 浏览量:10 字体大小: A+ A-

图片来自网络,版权属于原作者
来源:Offshore Energy 2026-4-22
翻译:国际海事信息网 杨皓然 张运鸿
挪威海底服务供应商DeepOcean已拿下中国台湾近海TPC海上风电场二期项目(TPC-II)阵列间电缆安装支持合同。
DeepOcean公司的服务范围包括安装阵列间电缆,以及工程和项目管理服务。
该离岸工程将借助租用的“Orient Adventurer”号水下作业船,与东方风能(Dong Fang Offshore)合作实施。该船已升级配备两台遥控潜水器(ROV)、一个甲板下转盘以及用于海底电缆铺设的电缆铺设装置。
4月22日,DeepOcean表示,在欧洲电缆铺设专家的支持下,旗下海上可再生能源团队将在当地负责项目执行管理工作。
据DeepOcean称,工程将立即启动,并于2026年内完工。
台电海上风电二期项目(TPC Phase II)是中国台湾省政府于2018年4月选定的11个海上风电项目之一。
该295兆瓦的项目位于中国台湾省彰化县鹿港外海6.5至20公里处,将在负压筒基础上安装31台丹麦风电巨头Vestas旗下的9.5兆瓦涡轮机。这些涡轮机将通过三条66千伏阵列间电缆环路连接至海上变电站,并通过三条输电电缆将电力输送至岸上。
首个负压筒基础已于2025年春季在项目现场安装完毕,随后海上风电场二期项目(TPC-II)中的海上变电站于去年8月建成。
(本文版权归国际海事信息网所有,图片版权归原作者,转载请注明出处。)
DeepOcean contracted for inter-array work on new Taiwanese offshore wind farm
DeepOcean has secured a contract for the installation support of inter-array cables at the TPC offshore wind farm phase 2 (TPC-II) offshore Taiwan.
The Norwegian company’s scope encompasses the installation of inter-array cables, as well as engineering and project management services.
The offshore work will be carried out with Dong Fang Offshore using the chartered subsea vessel Orient Adventurer, which has been upgraded with two ROVs, an under-deck carousel, and a cable lay spread for subsea cable installation.
Project execution will be managed locally by DeepOcean’s offshore renewables team, with support from European cable installation specialists, DeepOcean said on April 22.
The work will commence immediately and be completed during 2026, according to the company.
The Taipower Offshore Wind Project Phase II (TPC Phase II) was one of the eleven offshore wind projects selected by the Taiwanese government in April 2018.
The 295 MW project, located 6.5–20 kilometers off Lukang in Changhua County, will feature 31 Vestas 9.5 MW turbines installed on jacket foundations. The turbines will be connected via three 66 kV inter-array cable loops to an offshore substation, with power exported to shore through three export cables.
The first jacket foundation was installed at the project site in Spring 2025, followed by the TPC-II offshore substation in August last year.
来源:simic